Agile and Scrum
Why teams deliver software in small slices instead of one big release, how Scrum organises that into sprints with three roles and three lists, and what Agile means beyond Scrum.
In 30 seconds
Agile is the idea of building a product in short cycles: deliver a small working piece, get reactions, adjust, repeat. That way a wrong guess is found in weeks, not at the end of the project.
Scrum is the best-known recipe for it. A small team works in sprints of a month or less. A Product Owner orders the list of wanted work, Developers build the top of it, and a Scrum Master keeps the process healthy.
Each sprint ends by reviewing the result and how the team worked. Scrum is one agile method among several.
Agile and Scrum, step by step
Scrum terms follow the 2020 Scrum Guide, which calls the three roles “accountabilities” and counts the sprint itself as the fifth event. The Agile Manifesto values the items on the right too, only less.
- Step 1: One big delivery. One way to run a project is to plan everything up front, build for most of a year and deliver at the end. If what users need shifts in month 3, nobody finds out until month 12, because nothing usable reaches them earlier.
- Step 2: Deliver in small slices. The agile answer is to cut the same year into short cycles. Each one ends with a small piece of working product that users can try, and what they say shapes the next cycle. A change in month 3 is picked up in month 4.
- Step 3: The Scrum team. Scrum is the best-known recipe for working this way. Its team has three roles. The Product Owner decides what is most valuable to build next. The Developers, meaning everyone who does the work, build it. The Scrum Master helps the team use Scrum well and clears obstacles.
- Step 4: Backlogs and the increment. Scrum keeps three artifacts. The Product Backlog is one ordered list of everything the product might need, most valuable on top. The Sprint Backlog holds the items the team takes on next, plus a plan. The Increment is the finished, usable result.
- Step 5: One sprint. Work happens in sprints: fixed-length cycles of a month or less, often two weeks. Sprint Planning opens the sprint. A 15-minute Daily Scrum keeps the team in step. At the end the Sprint Review shows the result to the people it is for, and the Retrospective looks at how the team worked.
- Step 6: Inspect and adapt. Each sprint closes two feedback loops. In the Sprint Review, reactions to the Increment change what sits on top of the Product Backlog. In the Retrospective, the team changes how it works. Then the next sprint starts, so a wrong turn costs weeks, not a year.
- Step 7: Agile is bigger than Scrum. Agile is not a method. It is a set of four values and twelve principles written down in 2001, favouring working software, close contact with customers and openness to change. Scrum is one way to follow them. Kanban, which has no sprints, and Extreme Programming, which adds engineering practices, are others.
Try it yourself
Learn this first
Nothing. This concept starts from scratch.
Learn next
- Git branching strategiesGit Flow against trunk-based development: where work branches, merges and gets released. Beginner
- Feature flagsShip code switched off, then turn it on for a few users, then for everyone. Beginner
- Test-driven developmentFailing test, passing code, tidy-up: a leap-year function grown in small rounds. Beginner